Button Text
Glossary

Milestone Trend Analysis

Milestone Trend Analysis (MTA) is a method in project management that is used to monitor and control the progress and scheduling of a project. It involves comparing the planned and actual milestone dates and displaying them in a chart. Milestone Trend Analysis is an effective tool for early identification of risks and potential delays and for initiating appropriate countermeasures.

Basics of Milestone Trend Analysis

Milestone Trend Analysis is based on the comparison of planned and actually achieved milestone dates. A milestone is an important interim step in a project that marks the completion of a certain phase or the achievement of a significant partial result. Therefore, adherence to milestone dates is an indicator of a project's success and compliance with the overall schedule.

In MTA, the planned milestone dates are compared with the actual or forecasted dates. The difference between the two values is referred to as a time deviation. These deviations are displayed in a milestone trend chart, which shows the course of time deviations for each milestone throughout the entire project duration.

Creating a Milestone Trend Chart

To create a milestone trend chart, the following steps are carried out:

     
  1. Defining the milestones: First, the key milestones of a project are identified and their planned dates are set. Typically, these dates are defined during project planning and recorded in the project schedule or in the timeline.
  2.  
  3. Determining the actual dates: In the course of the project, the actual milestone dates are determined and documented. This data can be taken, for example, from the project progress report or the project status report.
  4.  
  5. Calculating the deviations: For each milestone, the time deviation between the planned and the actual date is calculated. Positive deviations indicate that a milestone was reached earlier than planned, while negative deviations point to delays.
  6.  
  7. Representation in the chart: The determined deviations are displayed in a milestone trend chart. The time deviation is plotted on the vertical axis and the point of analysis on the horizontal axis. The individual milestones are represented by lines or points in the chart.

Evaluation and Interpretation of Milestone Trend Analysis

The milestone trend chart shows the course of time deviations for each milestone over time. Various trends and patterns can be recognized, allowing conclusions to be drawn about the project's schedule situation:

     
  • Stable milestones: If the time deviation of a milestone remains constant over the entire project duration, these are referred to as stable milestones. This indicates that the project planning is realistic and the project's schedule situation is under control.
  •  
  • Increasing delays: If the milestone trend chart shows a continuous increase in time deviations for one or more milestones, this suggests problems or risks in the project leading to delays. In this case, appropriate countermeasures should be taken to improve the schedule situation.
  •  
  • Sudden changes: If the time deviation of a milestone suddenly rises or falls sharply, this can be due to special events or decisions in the project. Such changes should be analyzed and assessed to identify possible impacts on the overall project.

Therefore, Milestone Trend Analysis is an effective tool for continuously monitoring the progress of a project and for early detection of potential risks or delays. By regularly updating the milestone trend chart, trends and developments in the project's course can be observed and appropriate countermeasures can be initiated to ensure adherence to schedule objectives.

Read more

Related articles

No items found.